We will now be replacing the gas main in Mitre Tavern Yard next Tuesday, as there is a cable laying on top of the main which we cannot cut, causing the delay.
We anticipate that reinstatement works and this phase of works will still be completed by the end of next week.
We will keep you updated on our progress.
Thank you to anyone affected and for your continued patience whilst we carry out these essentials works.