Staying in touch before the weekend

By Market Place

Works are progressing in Market Place and we now have no more than 15 metres of digging left to go.

We will be tarmacking Market Place today and then tomorrow the junction where Market Place meets Kings Arms Street should reopen and there will be then seven to eight parking bays available.

We anticipate works should be completed by next weekend and then reinstatement work will be carried out.

Thank you to everyone affected for your continued patience whilst we carry out these essential works.

 

 

Works update

By Church Street

We anticipate that we will be carrying out works at the junction where Market Place meets Church Street this Friday and over this weekend. The junction where Market Place meets Church Street will remain closed whilst we carry out works. One lane will be left open on Church Street for traffic to come down the road still.

This Thursday, the junction where Market Place meets King’s Arms Street will reopen.

Works should be completed towards the end of next week or at the start of the week after.

 

Works still on hold

By Mitre Tavern Yard

We are continuing to review when work can commence in Mitre Tavern Yard, however due to the COVID-19 situation, we are uncertain if work will commence in mid-May.

Thank you for your continued patience. We will provide further updates on works commencing as soon as we have any.

 

Works ahead of schedule

By Market Place

We are currently a week ahead of schedule and have now tarmacked half of Market Place, with 20 metres of digging left to go.

We anticipate that we will be working at the junction where Market Place meets Church Street at the end of this week and this end of Market place will still remain closed. On Thursday or Friday the junction where Market Place meets King’s Arms Street will reopen again.

Over the weekend we will start works in Church Street.

We anticipate that this phase of works will be completed by the end of next week or by the start of the week commencing 18 May.

Thank you to everyone affected by our works and for your continued patience whilst we carry out these essential works.

Phase 3 work is progressing

By Church Street
Works are currently progressing down Market Place and we are currently still on schedule to carryout works at the junction where Market Place meets Church Street in a couple of weeks. We will keep you updated on our progress over the next couple of weeks.

Work is progressing

By Market Place

Works are progressing down Market Place and Phase three is currently still on schedule to complete within the next four weeks. We will provide further updates as soon as we have any.

Thank you for your continued patience whilst we carry out these works and to anyone who is affected by our works.

Phase 3 works update

By Market Place

Work is continuing in Market Place and is on schedule as we are now digging up the old main in the middle of the road. We have approximately 50m to go in total and anticipate that the works will take no longer than four more weeks to complete.

We will keep you regularly updated on our progress. Thank you to everyone for your patience whilst we carry out these essential works.

Update statement

By Mitre Tavern Yard

Thank you all for your patience. We just wanted to say that we are continuing to review when we may be able to restart work. We are hoping, depending on the wider COVID-19 situation, that we might be able to be back in Mitre Tavern Yard in mid-May although things are still uncertain. As soon as we have any further news, we’ll come back to you.

Staying in touch before the weekend

By Market Place

Work continues as planned in Market Place and we’ll be working over the weekend again in order to keep on schedule. We anticipate being close to the junction with Church Street in approximately two weeks’ time. As we get nearer, and Market Place becomes narrower, we may find increased congestion of services underground. However, we’ll keep you posted on this and let you know if this slows us down. At the moment we still have about 100m to go in total and anticipate the road closure continuing until the end of May.

Once again, thank you to everyone affected by our work. We appreciate your patience while we carry out this essential work.