Today Market Place has been closed at the junction of Church Street and junction of Kings Arms Street.

There is limited access only for small delivery vehicles at Kings Arms Street to park and manoeuvre by the Market Cross for delivery to the few shops that are still open.

Market Place will be closed for around four weeks and parking will be suspended temporarily outside shops. The free two hour parking remains in place for shoppers in Bank Loke and Vicarage Street car parks.

We will keep you regularly updated on our progress over the next few weeks.

Phase 3 works update

By Market Place

Once we have reopened Market Street early next week, we will be closing Market Place at the junction of Church Street and at the junction of Kings Arms Street. During the Phase 3 of works, there will be no left turn into Market Place. There will be limited access for small delivery vehicles at Kings Arms Street to park and manoeuvre by the Market Cross for delivery to the few shops that will be still open.

Parking will be suspended temporarily outside shops during this phase of works. The free two hour parking remains in place for shoppers in Bank Loke and Vicarage Street car parks.

Ongoing works

By Market Place, northWalsham

We have completed work half way down Market Place, but still need to dig up the old main which is in the middle of the road. We will provide further updates of our progress next week.

Works started

By Market Place

We are currently outside No.31, where we will make another temporary connection which will be drilled on Friday 3 April. Then once King Arm’s Street is complete we should be able to remove the road closure.

We will publish further information on a regular basis in order to keep you up to date with what is happening.

Welcome to your updates for Market Place

By Market Place

We will be starting work on Monday 24 February 2020. We will be replacing approximately 210m of existing gas pipe from the junction of Market Street to the junction of Church Street. We anticipate that this section of road will be closed for approximately five weeks. During this time traffic management will be in place, with a possibility of road closure.

We will publish further information on a regular basis in order to keep you up to date with what is happening.