Update on works

By Kings Arms Street

Kings Arms Street should be re-opened next Monday or Tuesday. This delay is due to us not being able to get hold of materials until tomorrow. Reinstatement work should then take place this weekend. We will update you on our progress next week.

 

Project update

By Kings Arms Street

Work on King Arm’s Street is still currently delayed. This is due to a knock on affect from some major problems we had at the Mundesley Road junction.

 

We will provide further information once we have more information.

Work delayed

By Kings Arms Street

Work on King Arm’s Street was due to start on Monday 24 February, however it is currently delayed and is yet to start. Work will not be due to start potentially for another three weeks.

We will provide further information on this road as to why there has been delays and when work is due to commence as soon as possible.

Welcome to your updates for Kings Arms Street

By Kings Arms Street

We will be starting work on Monday 24 February 2020. We will be replacing approximately 20m of existing gas pipe at the top of Kings Arms Street. This work will last for approximately five weeks but will only be carried out on Thursdays. During this time traffic management will be in place, with a possibility of road closure.

We will publish further information on a regular basis in order to keep you up to date with what is happening.