IMGM200088 - Isledon Court N7 0SE

Ready for hand-over

By August 19, 2019 No Comments

Please see updates to work:

  • A cut and test has been approved
  • A survey was requested on Friday 16 August due to asbestos being identified in building owners reports
  • Cadent have parking bay suspensions in use until Friday 23 August. Parking bay suspension have now been granted from Saturday 24 August
  • We have received the necessary permissions to commence and we are now in the process of planning the work in order to restore your gas. A job pack will now be put together and handed over to a site manager who will be responsible for overseeing and completing the operational aspect of the work.

We will provide an update once further information is available.