Please see updates to work:

  • A hand-over was planned for Thursday 29 August
  • The carpenter attended site on Thursday 29 August to give access for the cut and test n the basement for a new pick up route
  • The riser team was on site on Friday 30 August to start the cut and test,
  • The cut and test was passed and carpenters started boxing in on Saturday 31 August
  • The riser team and carpenter are due to be on site today – Monday 2 September

Current estimated completion date: Friday 6 September.