IMGM200062 - Morrit House HA0 4XD

Permissions received

By July 12, 2019 No Comments

Please see updates to work:

  • We have received the necessary permissions to commence and we are now in the process of planning the work in order to restore your gas. A job pack will now be put together and handed over to a site manager who will be responsible for overseeing and completing the operational aspect of the work
  • Parking bay suspensions have been requested and granted to start on Friday 19 July.

When further information is available, we will post an update.