Please see update of works:

  • The scaffold has been signed off
  • Riser operatives, fitters and carpenters have been on site since Friday 5 July
  • Welders are on site today – Tuesday 9 July for last entries, due to be commissioned tomorrow – Wednesday 10 July
  • In-ground operatives are on site today and their works are due to be commissioned today – Tuesday 9 July
  • Fitters will also be on site today continuing works.

Current estimated completion date: Friday 12 July.