IMGM200035 - Sussex Mansion SW7 3JZ

Awaiting confirmations

By May 21, 2019 No Comments

Current updates to works:

  • We have received the necessary permissions to commence and we are now in the process of planning the work in order to restore your gas. A job pack will now be put together and handed over to a site manager who will be responsible for overseeing and completing the operational aspect of the work
  • We are currently awaiting temp work to confirm the scaffolding in walkways. Once this has been confirmed, access can issue the scaffold design
  • Parking bay suspensions have been requested for Tuesday 28 May
  • We are currently awaiting for confirmation on design and the parking bay suspension.

Once more information is available we will post an update.