Ready for hand-over

By | IMGM200088 - Isledon Court N7 0SE

Please see updates to work:

  • A cut and test has been approved
  • A survey was requested on Friday 16 August due to asbestos being identified in building owners reports
  • Cadent have parking bay suspensions in use until Friday 23 August. Parking bay suspension have now been granted from Saturday 24 August
  • We have received the necessary permissions to commence and we are now in the process of planning the work in order to restore your gas. A job pack will now be put together and handed over to a site manager who will be responsible for overseeing and completing the operational aspect of the work.

We will provide an update once further information is available.

Ongoing work

By | IMGM200086 - 57 Stanhope Gardens SW7 5RF

Please see updates to work:

  • Parking bay suspensions are in hand with Cadent, If agreed a design will be required
  • A site meeting was arranged on Friday 16 August
  • A partial hand-over was completed Saturday 17 August
  • Riser work started on Saturday 17 August and is ongoing
  • A fitter will be on site today – Monday 19 August.

When new information is available we will provide an update.

 

Ongoing works

By | IMGM200083 - Mccarthy Road TW13 6UA

Please see updates to work:

  • Scaffold build started on Friday 16 August
  • Riser team has been booked in for 3 days starting from today – Monday 19 August
  • Carpenter will be on site today – Monday 19 August
  • Alterations to scaffold to commence starting tomorrow – Tuesday 20 August.

Current estimated completion date: Friday 23 August.

Ongoing works

By | IMGM200081 - Norcombe House N19 4RB

Please see updates to work:

  • A mobile elevated work platform has been arrange for tomorrow – Tuesday 20 August for top flat access.
  • Fitters are in site today – Monday 19 August for pre-work.

Current estimated completion date: Friday 23 August.

 

Survey to be revised

By | IMGM200078 - 19 Cleveland Square W2 6DG

Please see updates to work:

  • Revised planned route unachievable due to load baring wall, so a site meeting is to be arranged and a new route required
  • Land and planning confirmed no planning permission is required
  • Simon to attend site today – Tuesday 19 August for a revised survey.

 

An update will be provided as soon as we have new information.

 

Project update

By | IMGM200072 - The Water Gardens W2 2DD

Please see updates to work:

  • Asbestos removal to take place between Friday 23 August – Tuesday 27 August.
  • tRIIO to continue with cut and test from Wednesday 28 August as long as clearance certificates have been provided.

 

Once more information is available we will provide an update.